1. Administration -> Roles and Permissions – Update Role Permissions to Configure Calendar

a. Check off Configure Calendar under Time

 

 

 

 

 

 

 

 

 

 

 

 

 

2. Modeling -> Time – On the Time page, select Import Calendar

 

 

 

 

 

 

 

 

 

 

 

 

  1. Download Template and Update the dates and time stratum needed.

a. Insert additional columns if you need to add Day or Week stratums

 

 

 

 

 

 

 

 

  1. Choose Reload entire structure when changing the time stratum from monthly to weekly or monthly to daily. Choose Update if you only need to change the fiscal rollups.  Choose Append when you are adding new years to Adaptive.
  2. Update the Default Time Stratum if you need GL Accounts to be loaded to a time stratum other than Months.